Progress Billing Contracts

objective

The Progress Billing Contracts option is used to manage contracts and change orders based on a progress percentage, dollar amount or unit quantity. This option creates a link between invoicing, project management and the customer.

 

prerequisites

 

Icons

 

steps

maestro* > Invoicing > Contractual Billing > Progress > Progress Billing Contracts

 

Create a progress billing contract

  1. Enter the :
  1. Enter the required information in the Project Description tab:
    1. :
    1. :
    1. :
    1. :
    1. - This section displays the holdback amounts summary entered in the Billing Schedule tab:
  2. The Additional Fields tab allows the user to personalize the Progress Billing Contracts by adding fields. Click the Configuration button to do so.
  3. Enter the required information in the :
  1. Enter the required information in the :
  1. Click on Save.

 

see also

 